15/04/2015
The case of Malcolm Charles Contracts Ltd v Crispin and Another [[2014] All ER (D) 289] decided in November 2014 does much to re-iterate the long established position of the courts that when deciding whether parties to a contract have reached an agreement, an objective test will be applied.
The Facts of the Case
The proceedings related to an Adjudication concerning a building dispute. The Defendants invited the claimant construction company, Malcolm Charles Contracts Ltd (MCC), to tender for a contract to carry out work on their property.
After some six months of negotiations, on the 1st August 2011, the Defendants’ architect, Mr Elliott sent a blank copy of the proposed contract to the Defendants for their consideration. The proposed contract was the JCT HOO form described by Mr Elliott to Mr Crispin as "the proposed contract as agreed". Mr Crispin's evidence was that he read the document when he received it and the Court concluded that he would have understood the contents of the document.
A pre-contract meeting was held between the parties on the 9th August 2011. It is MCC's case that at this meeting the parties agreed a contract on the basis of the JCT HOO at a price of £369,861 with a commencement date of 9th September 2011(this was later moved to the 12th September 2011) and a contract period of 33 weeks. MCC also stated that at the meeting, Mr Elliott took the Defendants through the documents and drawings that would form the contract and that the parties reached agreement on the scope, price, time and payment mechanism for the venture, and all this was written down in the minutes of the meeting prepared by Mr Elliot.
Both Defendants contended that nothing at all was formally agreed at this meeting.
The Defendants argued that, as far as they were concerned:
Subsequently, in September 2011, the first defendant queried whether payment was in full on completion. MCC's representative replied, and asked who should be contacted to arrange for it to have keys to the property. The first defendant agreed that the keys should be collected from his father, and equipment and materials were then brought to the property.
On Thursday 8th September 2011 MCC’s foreman attended site to survey the structural steelwork and carry out an external level survey. This was not work that would have been carried out for pricing, or done if MCC did not believe they had they were contracted to the project.
During the weekend of 9th – 11th September 2011 MCC’s foreman and other staff took delivery of plant and materials to the site in preparation to start work on Monday 12th September 2011. They duly turned up for work on the stipulated start date and some temporary plumbing works were then carried out.
However, on Sunday 11th September 2011 Mr Crispin had sent an email to MCC and Mr Elliott in the following terms :
"We are not ready to start work until we have a proper contract; there are details in there that are not yet finalised.
My building insurance is not in place for construction and there are still cost issues and details that haven't been finalised. It would not be right or fair for parties involved to start work until everything is in good order. Please do not start work on Monday."
MCC sent the Defendants an invoice for £3,648.95 which represented the cost of the plumbing work done on the 12th September. The Defendants did not make any payment
On 2nd September 2012 agents for MCC wrote to the Defendants claiming payment for the aborted costs previously claimed and a further £60,000 or so for breach of contract. Again the Defendants did not make any payment.
The dispute was then referred to adjudication. The first adjudicator concluded that he had no jurisdiction to act (the reason for this decision was not given). The (second) adjudicator in a first ruling ruled that on 9th August 2011 the parties had concluded a contract under terms of the JCT HOO form.
The Defendant’s argued that as there was no construction contract in place, the second adjudicator lacked jurisdiction.
The Decision
In her decision, Carr J quoted from the Supreme Court decision of RTS v Molkerei Alois [2010] BLR 337;
"The Principles
45. The general principles are not in doubt. Whether there is a binding contract between the parties and if so, upon what terms depends upon what they have agreed. It depends not upon their subjective state of mind, but upon a consideration of what was communicated between them by words or conduct, and whether that leads objectively to a conclusion that they intended to create legal relations and had agreed upon all the terms which they regarded or the law requires as essential for the formation of legally binding relations. Even if certain terms of economic or other significance to the parties have not been finalised, an objective appraisal of their words and conduct may lead to the conclusion that they did not intend agreement of such terms to be a pre-condition to a concluded and legally binding agreement."
Carr J concluded that when looked at objectively, the words and conduct of the parties at the pre-contractual meeting on the 9th August 2011 resulted in a binding contractual agreement, the terms of which were evidenced by the minutes of the meeting. Therefore, the adjudicator’s jurisdiction could not be in doubt and his decision was upheld.
What This Means for Parties to an Adjudication
This case, along with RTS v Molkerei Alois makes it clear that parties to adjudication cannot take for granted that because they themselves did not believe that there was a binding contract between them, that the court, when applying an objective test, will take the same view. As long as one party can show that:
-
on the basis of the evidence, the reasonable man would say that the parties were in agreement and had intended to create legal relations (the test disregards the parties’ own views), and
-
the contract is sufficiently certain so as to be enforceable
then a court can conclude that a binding contract exists Dhanani v Crasnianski[2011] EWHC 926 , [2011] 2 All ER (Comm) 799).
It is therefore imperative that both parties are free from any uncertainty as to whether a construction contract exists between them. By ensuring that a contract has been executed in a clear, non-ambiguous way, parties will be able to confidently (albeit sometimes reluctantly) accept an adjudicator’s decision and save the time and money needed to confirm the adjudicator’s jurisdiction in a court of law.
If you would like to find out more about construction contracts and/or adjudication, please click here, or alternatively phone our London office on 0207 993 6960.
If you would like to make a comment on this blog please feel free to drop us a line in the comments section below.
Fisher Scoggins Waters is a leading construction, engineering and manufacturing litigation firm, specialising in disputes and disasters. For further information on this article or any of our litigation services, please contact us on: +44 (0) 207 993 6960.