Search

BLOG

Mr and Mrs Vainker v. Marbank Construction Ltd & Ors (2024) Technology and Construction Court (TCC)

Blog image

FSW Law

In the case of Mr and Mrs Vainker v. Marbank Construction Ltd & Ors [2024] EWHC 667 (TCC), the Technology and Construction Court (TCC) provided considered insights into the application of the Defective Premises Act 1972 (DPA).  Charlotte Waters of FSW-Law assisted Mr and Mrs Vainker in this successful claim.​

Case Background:

Mr and Mrs Vainker employed Marbank Construction Ltd as the main contractor and SCD Architects Ltd as the architect for building their new home in Twickenham.  During the build and after practical completion, they discovered several defects, especially safety-related issues, with the glass balustrades installed throughout the property.  They pursued claims against Marbank Construction Ltd and SCD Architects Ltd under the Defective Premises Act 1972 (DPA) because the dwelling was not fit for habitation.​ ​

Failure to Mitigate Allegations:

Marbank contended that the Vainkers failed to mitigate their losses by not providing Marbank the opportunity (by inviting it or allowing access) to rectify the defects before engaging another contractor for remedial work.The Court examined whether the Vainkers took reasonable steps to mitigate their losses and concluded that their decision to hire a different contractor for repairs and the delay in doing so was justified, given the circumstances.  The Court emphasized that while claimants have a duty to mitigate, they are not obligated to allow the original contractor to perform remedial work, especially when confidence in the contractor's ability to ascertain the cause of the defects and provide a suitable remedial scheme is uncertain.  Therefore, the Court rejected Marbank's argument regarding the Vainkers' alleged failure to mitigate.

This judgment underscores that homeowners are expected to take reasonable steps to mitigate damages but are not necessarily required to permit the original contractor to undertake remedial work, particularly when there are valid concerns about the contractor's performance.

Key Findings:

  1. Duty Under the DPA: The Court held that both Marbank and SCD had a duty under Section 1(1) of the DPA to carry out their work in a professional manner, using appropriate materials, ensuring the home would be habitable to live in once finished.
  2. Fitness for Habitation: The main question was whether the defects made the house uninhabitable.  The Court noted that while minor or cosmetic issues might not meet this standard, defects that pose health and safety risks, like inadequate glass balustrades, could make a home unfit.  In this case, using toughened 'exploding' glass instead of the specified toughened laminated glass in the balustrades was unsafe, violating the DPA.
  3. Net Contribution Clauses: The judgment examined whether net contribution clauses apply under the DPA.  It concluded that Section 6(3) of the DPA invalidates any contract terms that try to exclude or limit liability under the Act, including net contribution clauses.  This highlights the strong protection the DPA offers homeowners against attempts to reduce liability through contractual terms.

Limitation Periods: 

Although not a feature in this action as the DPA Claim was brought within the relevant limitation period applicable at the time, the Building Safety Act 2022 extended the time limit for bringing DPA claims, giving homeowners more time to seek remedies for defective work. 

Conclusion:

The Vainker v. Marbank Construction Ltd & Ors case is a key example of construction professionals' responsibilities under the DPA.  It underscores the need for contractors and architects to strictly follow professional standards and specifications to ensure that completed homes.

Follow our company page on linkedin for future updates and our views on the latest developments

Please leave a comment

Enter the name you would like to appear on the comment.
(required)
Enter the email you would like to use to get updates. You email is not visible and can not be used by other users.
(required)
Enter you comment help.

 
  Post Comment

Book Launch - 27 November 2019

Will you be joining us?

HSE and Environment Agency prosecution: A new climate

27 November 2019 | Bloomsbury, 50 Bedford Square, London, WC1B 3DP

Event Registration

First name
Surname
Email address
Any additional information
Post/Event URL
Post/Event Title
CAPTCHA image
Enter the code shown above in the box below.

Tag Cloud

‘fit for purpose’ obligations 2016 Adjudication adjudication lawyer Adjudication Notice Adjudication process appeal appointing an adjudicator Arbitration Artificial Intelligence Asbestos benefits of off-site construction bonfires book launch breach of contract Brexit Building Defects business interruption Business Interruption Insurance CDM CDM Regulations chambers and partners Charlotte Waters civil proceedings claim payments Claims client COMAH commercial contracts complex construction claims Compliance compulsory sprinklers in warehouses consequential loss construction Construction Construction & Engineering construction contract Construction contract dispute Construction contracts Construction dispute construction dispute lawyer construction dispute resolution construction dispute resolution solicitor construction dispute solicitors Construction Disputes Resolution Construction industry Construction Magazine contracts Contribution claim Corporate Manslaughter Corporate Responsibility costs criminal investigation criminal proceedings cut out fuse Defective Building Work Defective Premises Act developer developers disadvantages of off-site construction Disaster disaster claim Disasters Dispute dispute resolution Disputes DPA Dr Louise Smail Emergency response Emergency Response Solicitors enforcement notices Engineering Engineering dispute Environment Agency environment law Environmental Environmental Agency Environmental damage Environmental Law environmental waste EU EU Procurement Europe Evidence Expert evidence expert witness falls from height Fatal Accidents fee for intervention Fees For Intervention FFI FIDIC Contracts fine Fines Fire Fire Claim fire claims fire damage fire damage lawyers fire sprinkler systems fireworks flood flood claim flood damage food hygiene Fracking fracking claims Fraudulent claims FSW Gross Negligence Manslaughter Guide to Adjudication H&S fine increases; health and safety fines; Health & Safety health & safety breach health & safety sentences health & safety sentencing guidelines health & safety sentencing large corporations health and safety health and safety Health and Safety Executive heave Higher Fines Honey Rose v R How to appoint an adjudicator HSE Insolvency insolvent insurance Insurance Act 2015 insurance bill Insurance Broker insurance claim insurance cover Insurance Disclosure Insurance Disclosure insurance dispute insurance dispute solicitors Insurance Warranties ISO 45001 join us joint venture Judicial Review latest news Law Lawyer legal 500 legal advice privilege Legal Expense Insurance legal professional privilege legal retainers Liability Liquidated Damages Litigation litigation privilege local bodies magistrates’ courts Major Property Damage Manufacturing Martinisation material breach Mediation Michael Appleby Micheal appleby modern methods of construction (MMC) modular construction Mr. Gutaj Notice of adjudication panel firms party wall Performance Bond planning powers of an adjudicator pre-fabrication procurement procurement injunction procurement model Property Damage property danage Public Contract Public Contracts Public Contracts Regulations public procurement public procurement challenges public procurement relationship public sector Publicity Order PUWER recruitment regulation 11 Relief Resolution riot Riot Compensation Act 2016 Risk Risk Assessment safety in the workplace Sanctions Self-build sentence sentencing sentencing guidelines Serious Fraud Office SME Sneller Sony specialist risk and safety consultant Statute Barred Sub-Contractors subrogation subsidance subsidence TCC TCC Guidance team Technology and Construction Court The Adjudicator’s Decision and Costs The Enterprise Act The Lord Young Reforms The Powers Of An Adjudicator The Public Contracts Regulations 2015 The referral notice and response Training tree root UK Underwriters Warehouse insurance Warranties waste water damage WEEE What is Adjudication? what should an adjudication refal notice contain work equipment

Search The Site

Accreditations

 

UK Leading Firm 2025


Contact Us Now For Advice And Guidance

Enter your name
Enter your surname
Enter your Email
Ask us a Question?