Search

BLOG

New Guidance Issued By TCC On Public Procurement Cases

Blog image

In July 2017, the Technology and Construction Court (TCC) issued a new guidance note on public procurement cases (the TCC Guidance).

The key aims of the TCC Guidance are to:

  • minimise the risk of parties issuing proceedings by encouraging public bodies to talk openly with providers and share key documents          

  • provide consistency on common procedural issues relating to public procurement          

  • reduce legal costs for all parties by ensuring experienced judges are appointed alongside expert court staff to deal with public procurement cases

Avoiding litigation proceedings in public procurement cases


In public procurement disputes, the mandatory standstill period is a mere 10 days.  This leaves limited time for any pre-action process.  A potential claimant may need to commence proceedings without delay to obtain an automatic suspension of the award of the contract.

Because of the short time-period, there is likely to be a major imbalance of information held between the parties.

To address this problem, the TCC Guidance sets out the following recommended pre-action process:

1.    The potential claimant will send a letter before claim to the contracting authority.  This letter should alert the authority to the reason for the claim, the procurement process it relates to, any further information they require, the remedy sought and any request for an extension of the standstill period and/or a request not to enter into the contract for a specific period of time and/or not to do so without a specified period of notice to the potential claimant.

2.    The authority needs to acknowledge the letter and let the claimant know whether the standstill period will be extended, and if so, by how long.  Disclosure of any information requested by the potential claimant should be given.

3.    The parties should continue to try and resolve the dispute without resorting to litigation.

The TCC Guidance emphasises strongly that both parties need to operate under a culture of co-operation and reasonableness when dealing with matters such as granting extensions of time and standstill periods.

Confidentiality and disclosure in public procurement disputes

The TCC Guidance acknowledges that the disclosure of highly sensitive, confidential information can affect a disputing parties’ ability to resolve issues outside formal proceedings.  However, it states that 

“the need to protect confidential information needs to be balanced by the basic principle of open justice.”

Parties should also be ready to offer disclosure of documents, although consideration of any genuine concerns with regard to confidentiality, whether their own or those of third parties will need to be taken into account.  The TCC Guidance encourages authorities to disclose key materials to claimants at a very early stage (such as during pre-action correspondence) when relevant to the complaint.  This should reduce the need for claimants to incur the cost of making a court application to obtain this information.

The TCC Guidance also advocates for confidentiality rings to be established as early as possible.   A confidentiality ring comprises persons to whom documents containing confidential information may be disclosed based on their undertakings to preserve confidentiality.  Both parties’ legal advisors and counsel will be admitted into the ring.

Judicial Review

To reduce cost and complexity, if a claimant chooses to launch proceedings in the TCC and the Administrative Court (as a Judicial Review), both cases should be heard together in the TCC by a judge with an understanding of both processes.

Interested parties

Procurement claims frequently impact parties other than the claimant and the contracting authority, in particular, the successful bidder, who may be significantly affected by the relief sought in a procurement claim.

The TCC Guidance recommends that successful bidders should be put on notice if a procurement challenge is brought and they should apply to the TCC if they wish to be represented.

Interested parties may be entitled to recover some of their costs, or even, in some circumstances, be ordered to pay the costs of other parties.  Therefore, a careful risk assessment by the interested party’s solicitor needs to take place prior to proceedings.

The new Guidance will be incorporated as an annex to the TCC Guide, and therefore, it will not have the status of binding procedural rules.  However, judges will take the TCC Guidance into account, especially when looking at case management and the allocation of costs.

Fisher Scoggins Waters are a London based law firm who are experts in construction, manufacturing and engineering law.  If you would like more information making a claim following a public procurement process, please phone us on 0207 993 6960.

Follow our company page on linkedin for future updates and our views on the latest developments

Categories: Public Procurement

Please leave a comment

Enter the name you would like to appear on the comment.
(required)
Enter the email you would like to use to get updates. You email is not visible and can not be used by other users.
(required)
Enter you comment help.

 
  Post Comment

Book Launch - 27 November 2019

Will you be joining us?

HSE and Environment Agency prosecution: A new climate

27 November 2019 | Bloomsbury, 50 Bedford Square, London, WC1B 3DP

Event Registration

First name
Surname
Email address
Any additional information
Post/Event URL
Post/Event Title
CAPTCHA image
Enter the code shown above in the box below.

Tag Cloud

‘fit for purpose’ obligations 2016 Adjudication adjudication lawyer Adjudication Notice Adjudication process appeal appointing an adjudicator Arbitration Artificial Intelligence Asbestos benefits of off-site construction bonfires book launch breach of contract Brexit Building Defects business interruption Business Interruption Insurance CDM CDM Regulations chambers and partners Charlotte Waters civil proceedings claim payments Claims client COMAH commercial contracts complex construction claims Compliance compulsory sprinklers in warehouses consequential loss construction Construction Construction & Engineering construction contract Construction contract dispute Construction contracts Construction dispute construction dispute lawyer construction dispute resolution construction dispute resolution solicitor construction dispute solicitors Construction Disputes Resolution Construction industry Construction Magazine contracts Contribution claim Corporate Manslaughter Corporate Responsibility costs criminal investigation criminal proceedings cut out fuse Defective Building Work Defective Premises Act developer developers disadvantages of off-site construction Disaster disaster claim Disasters Dispute dispute resolution Disputes DPA Dr Louise Smail Emergency response Emergency Response Solicitors enforcement notices Engineering Engineering dispute Environment Agency environment law Environmental Environmental Agency Environmental damage Environmental Law environmental waste EU EU Procurement Europe Evidence Expert evidence expert witness falls from height Fatal Accidents fee for intervention Fees For Intervention FFI FIDIC Contracts fine Fines Fire Fire Claim fire claims fire damage fire damage lawyers fire sprinkler systems fireworks flood flood claim flood damage food hygiene Fracking fracking claims Fraudulent claims FSW Gross Negligence Manslaughter Guide to Adjudication H&S fine increases; health and safety fines; Health & Safety health & safety breach health & safety sentences health & safety sentencing guidelines health & safety sentencing large corporations health and safety health and safety Health and Safety Executive heave Higher Fines Honey Rose v R How to appoint an adjudicator HSE Insolvency insolvent insurance Insurance Act 2015 insurance bill Insurance Broker insurance claim insurance cover Insurance Disclosure Insurance Disclosure insurance dispute insurance dispute solicitors Insurance Warranties ISO 45001 join us joint venture Judicial Review latest news Law Lawyer legal 500 legal advice privilege Legal Expense Insurance legal professional privilege legal retainers Liability Liquidated Damages Litigation litigation privilege local bodies magistrates’ courts Major Property Damage Manufacturing Martinisation material breach Mediation Michael Appleby Micheal appleby modern methods of construction (MMC) modular construction Mr. Gutaj Notice of adjudication panel firms party wall Performance Bond planning powers of an adjudicator pre-fabrication procurement procurement injunction procurement model Property Damage property danage Public Contract Public Contracts Public Contracts Regulations public procurement public procurement challenges public procurement relationship public sector Publicity Order PUWER recruitment regulation 11 Relief Resolution riot Riot Compensation Act 2016 Risk Risk Assessment safety in the workplace Sanctions Self-build sentence sentencing sentencing guidelines Serious Fraud Office SME Sneller Sony specialist risk and safety consultant Statute Barred Sub-Contractors subrogation subsidance subsidence TCC TCC Guidance team Technology and Construction Court The Adjudicator’s Decision and Costs The Enterprise Act The Lord Young Reforms The Powers Of An Adjudicator The Public Contracts Regulations 2015 The referral notice and response Training tree root UK Underwriters Warehouse insurance Warranties waste water damage WEEE What is Adjudication? what should an adjudication refal notice contain work equipment

Search The Site

Accreditations

 

The Legal 500 - The Clients Guide to Law Firms


Contact Us Now For Advice And Guidance

Enter your name
Enter your surname
Enter your Email
Ask us a Question?