Search

BLOG

J Murphy & Sons v W Maher and Sons and its Points on Adjudication

Blog image

In the case of J Murphy & Sons v W Maher and Sons [2016] EWHC 1148 (TCC), [2016] All ER (D) 176 (May), Sir Robert Akenhead in the Technology and Construction Court (TCC) considered the status of a dispute concerning a full and final settlement of a final account. J. Murphy & Sons Ltd (“Murphy”) challenged the jurisdiction of an Adjudicator on the basis that the dispute referred to him had arisen under the terms of a settlement agreement that was distinct from the sub-sub-contract and therefore did not fall under that sub-sub-contract’s adjudication clause.

The facts of the case

The claimant (Murphy) and its subcontractor (Maher) were parties to a contract which incorporated NEC 3 Engineering and Construction Subcontract form. This included option W2 which provided for adjudication for any dispute 'arising under or in connection' with the contract.

 

Unusually, in the Subcontract Data section, the adjudicator nominating body was identified as the Technology and Construction Court (TCC), which cannot appoint adjudicators.

 

After Maher issued its final account application, the parties negotiated and eventually agreed a reduced final account sum of £720,000. This was confirmed by email.  Murphy never paid so Maher issued a notice of adjudication pursuant to clause W2 of the contract and stated that, as the TCC was not a nominating body, it would be applying to the Royal Institute of Chartered Surveyors (RICS) to nominate an adjudicator.

Murphy wrote to the appointed adjudicator raising two jurisdictional issues:

1.    there was no contractual basis for Maher to apply to RICS

2.    the adjudicator had no jurisdiction to deal with a dispute in relation to the alleged settlement agreement, which would have to be determined through the courts

 

Maher did not accept the second argument and, taking a pragmatic approach, served a second notice under the scheme for construction contracts (the scheme) rather than the contract. This was due to reliance on section 108 of the Housing Grants, Construction and Regeneration Act 1996 (HGCRA 1996) which provides that, where the contractual adjudication clauses do not comply with HGCRA 1996, s 108 (1)–(4), disputes 'arising under the contract' will be subject to the provisions of the scheme.

 

The issues to decide

 The TCC had to decide whether:


1.    the adjudication provisions within the sub-sub-contract were deficient, allowing the Scheme to apply; and

2.    a dispute regarding the alleged settlement agreement was a dispute “under” the sub-sub-contract.

 

The decision


The court considered that, even though the TCC was wrongly given as the nominating body under the contract, the adjudication clauses were compliant with HGCRA 1996, ss 108 (1)–(4), as these did not require a named adjudicator appointing entity.  The parties had agreed that adjudication would apply and, in the absence of agreement on a particular individual, an institution such as the RICS or the Institution of Civil Engineers should be nominated to make the appointment.

It was also accepted by the court that the adjudication clauses were broad enough to cover a dispute arising under the settlement agreement which 'undoubtedly arose in connection with the original [contract]'.

Sir Robert Akenhead also considered whether such a dispute could also be said to arise 'under' the contract and concluded that it did.  In his view, as a matter of common sense, neither Parliament or commercial entities would desire that parts of a business relationship or dispute would be decided by one institution and others by another.

 

The TCC considered that this logic should be extended to adjudication cases, particularly as parties commonly agreed interim or final accounts in some binding way and it would be 'extraordinary and illogical' that an Adjudicator could have jurisdiction to determine what entitlement a contractor might have to payment in all circumstances except where a dispute arose to whether that entitlement had been settled.

 

In summary

This decision confirms that both contractors and sub-contractors can rely on adjudication in disputes arising from agreements as to interim or final accounts where such agreements are considered binding in some way.  However, the learned judge did remark that he would be “sympathetic” to an application for an appeal, as previous case law has left some uncertainty in this area and the Court of Appeal could provide some much needed clarity.

Fisher Scoggins Waters are a London based law firm who are experts in environmental, construction, manufacturing and engineering matters.  If you need legal advice regarding adjudication, please phone us on 0207 993 6960.

Follow our company page on linkedin for future updates and our views on the latest developments

Please leave a comment

Enter the name you would like to appear on the comment.
(required)
Enter the email you would like to use to get updates. You email is not visible and can not be used by other users.
(required)
Enter you comment help.

 
  Post Comment

Book Launch - 27 November 2019

Will you be joining us?

HSE and Environment Agency prosecution: A new climate

27 November 2019 | Bloomsbury, 50 Bedford Square, London, WC1B 3DP

Event Registration

First name
Surname
Email address
Any additional information
Post/Event URL
Post/Event Title
CAPTCHA image
Enter the code shown above in the box below.

Tag Cloud

‘fit for purpose’ obligations 2016 Adjudication adjudication lawyer Adjudication Notice Adjudication process appeal appointing an adjudicator Arbitration Artificial Intelligence Asbestos benefits of off-site construction bonfires book launch breach of contract Brexit Building Defects business interruption Business Interruption Insurance CDM CDM Regulations chambers and partners Charlotte Waters civil proceedings claim payments Claims client COMAH commercial contracts complex construction claims Compliance compulsory sprinklers in warehouses consequential loss construction Construction Construction & Engineering construction contract Construction contract dispute Construction contracts Construction dispute construction dispute lawyer construction dispute resolution construction dispute resolution solicitor construction dispute solicitors Construction Disputes Resolution Construction industry Construction Magazine contracts Contribution claim Corporate Manslaughter Corporate Responsibility costs criminal investigation criminal proceedings cut out fuse Defective Building Work Defective Premises Act developer developers disadvantages of off-site construction Disaster disaster claim Disasters Dispute dispute resolution Disputes DPA Dr Louise Smail Emergency response Emergency Response Solicitors enforcement notices Engineering Engineering dispute Environment Agency environment law Environmental Environmental Agency Environmental damage Environmental Law environmental waste EU EU Procurement Europe Evidence Expert evidence expert witness falls from height Fatal Accidents fee for intervention Fees For Intervention FFI FIDIC Contracts fine Fines Fire Fire Claim fire claims fire damage fire damage lawyers fire sprinkler systems fireworks flood flood claim flood damage food hygiene Fracking fracking claims Fraudulent claims FSW Gross Negligence Manslaughter Guide to Adjudication H&S fine increases; health and safety fines; Health & Safety health & safety breach health & safety sentences health & safety sentencing guidelines health & safety sentencing large corporations health and safety health and safety Health and Safety Executive heave Higher Fines Honey Rose v R How to appoint an adjudicator HSE Insolvency insolvent insurance Insurance Act 2015 insurance bill Insurance Broker insurance claim insurance cover Insurance Disclosure Insurance Disclosure insurance dispute insurance dispute solicitors Insurance Warranties ISO 45001 join us joint venture Judicial Review latest news Law Lawyer legal 500 legal advice privilege Legal Expense Insurance legal professional privilege legal retainers Liability Liquidated Damages Litigation litigation privilege local bodies magistrates’ courts Major Property Damage Manufacturing Martinisation material breach Mediation Michael Appleby Micheal appleby modern methods of construction (MMC) modular construction Mr. Gutaj Notice of adjudication panel firms party wall Performance Bond planning powers of an adjudicator pre-fabrication procurement procurement injunction procurement model Property Damage property danage Public Contract Public Contracts Public Contracts Regulations public procurement public procurement challenges public procurement relationship public sector Publicity Order PUWER recruitment regulation 11 Relief Resolution riot Riot Compensation Act 2016 Risk Risk Assessment safety in the workplace Sanctions Self-build sentence sentencing sentencing guidelines Serious Fraud Office SME Sneller Sony specialist risk and safety consultant Statute Barred Sub-Contractors subrogation subsidance subsidence TCC TCC Guidance team Technology and Construction Court The Adjudicator’s Decision and Costs The Enterprise Act The Lord Young Reforms The Powers Of An Adjudicator The Public Contracts Regulations 2015 The referral notice and response Training tree root UK Underwriters Warehouse insurance Warranties waste water damage WEEE What is Adjudication? what should an adjudication refal notice contain work equipment

Search The Site

Accreditations

 

The Legal 500 - The Clients Guide to Law Firms


Contact Us Now For Advice And Guidance

Enter your name
Enter your surname
Enter your Email
Ask us a Question?