Search

BLOG

Multiple Construction Disputes and Adjudication – An Analysis of Deluxe Art & Theme v Beck Interiors

Blog image

In early February 2016, Mr Justice Coulson  handed down judgment in the case of Deluxe Art & Theme Limited v Beck Interiors Limited [2016] EWHC 238 (TCC). The case is of significance because it is the first time the Court has provided guidance on a wider interpretation of Paragraph 8(1) of the Scheme for Construction Contracts (England and Wales) Regulations 1998, which deals with the adjudication of more than one dispute from the same parties.

Up until this decision, it was well established that:

a)      Where there is an attempt to refer more than one dispute in a single notice of adjudication without consent, and the relevant adjudication rules (including the Scheme) do not permit this, such a course will likely render any decision unenforceable.

b)      If on examination what appears to be a single dispute, is in fact, an attempt to re-adjudicate a dispute decided by a previous adjudicator, any decision will be deemed unenforceable. This is because the first Adjudicator’s decision is binding (assuming, of course, the Adjudicator appointed does not resign, which would be the correct course of action).

Deluxe Art & Theme Limited v Beck Interiors Limited has clarified that where there is an attempt to refer two or more disputes to the same Adjudicator under separate notices of adjudication at the same time without consent, and the relevant adjudication rules do not permit this, then the second decision (ie the one referred in breach of paragraph 8(1) of the Scheme) is unenforceable.

The Facts of Deluxe Art & Theme v Beck Interiors

 Deluxe Art submitted two notices of adjudication commencing two separate adjudications. The first (Adjudication Two) was submitted on 22nd October 2015. Adjudication Two concerned a claim for an extension of time and loss and expense.  Delux Art then started a second adjudication (Adjudication Three) in a notice of adjudication dated 9th November 2015. Adjudication Three was thus started during the currency of Adjudication Two. Adjudication Three concerned Deluxe Art’s claim to release of the first half of retention following practical completion of its works. Both adjudications were under the Scheme.

The same Adjudicator was appointed for both disputes.  This meant the Adjudicator had to deal with both adjudications within overlapping timeframes.

Beck Interiors objected to the Adjudicators appointment stating they would not consent to him dealing with two disputes at the same time.

 

The decision in Adjudication Two was given on 4th December 2015. The decision in Adjudication Three was given on 11th December 2015. 

Beck Interiors refused to recognise either decision.  They argued that their objection to the Adjudicator hearing both decisions at the same time rendered the decisions reached unenforceable.   Paragraph  8(1) of the Scheme required Beck’s consent to the same adjudicator dealing with more than one dispute, and Beck did not so consent.

Beck also claimed that the overlapping timetables, which led to both decisions being made just a week apart meant there was a breach of natural justice rendering both decisions unenforceable because:

  • Dealing with both disputes at the same time led to confusion about what material was being submitted for which adjudication; and           

  • Having to deal with two adjudications running in parallel meant that there was a breach of natural justice in that Beck was rushed into putting in a rejoinder in Adjudication Two

 

The Decision

 

Deluxe Art tried to argue that there was only one dispute, an angle that was quickly rejected. 

With regards to the prohibition of two or more disputes being heard at the same time without party consent Coulson J stated:

I cannot accept that, in some way, the words of paragraph 8(1) relate only to the situation whether there are a number of different disputes on the same piece of paper (the adjudication notice), and not to the situation where there are a number of different disputes on many different such pieces of paper. That makes no sense. Moreover, there is nothing in paragraph 8(1) to allow such fine distinctions to be drawn. Whilst these type of points have only ever arisen before in cases where there was a single notice of adjudication that is pure happenstance.”

It was held that if a party wanted to refer more than one dispute to adjudication at any one time under the Scheme, it would have to secure the appointment of different adjudicators.

Coulson J also declared that there was no breach of natural justice in Adjudication Two. Beck had asked for more time to submit a rejoinder, had got such an extension, and had submitted a rejoinder accordingly. Adjudicators' case management powers to fix their own procedure had to be respected by the Court.

Adjudication Two would be enforced. Adjudication Three was a nullity for being carried out in breach of paragraph 8(1) of the Scheme and would therefore not be enforced.

In Summary

Following this decision, parties to adjudication now need to be aware an Adjudicator cannot be appointed under the Scheme for Construction Contracts (England and Wales) Regulations 1998, as amended, to deal with two separate disputes set out in two separate Notices of Adjudication at the same time, unless both parties consent.

Fisher Scoggins Waters are a London based law firm who are experts in construction, manufacturing and engineering matters.  We act for both employers and contractors and are regarded as one of the best construction dispute resolution firms in the UK.  If you would like to discuss any points raised in this article, please phone us on 0207 993 6960.

Follow our company page on linkedin for future updates and our views on the latest developments

Please leave a comment

Enter the name you would like to appear on the comment.
(required)
Enter the email you would like to use to get updates. You email is not visible and can not be used by other users.
(required)
Enter you comment help.

 
  Post Comment

Book Launch - 27 November 2019

Will you be joining us?

HSE and Environment Agency prosecution: A new climate

27 November 2019 | Bloomsbury, 50 Bedford Square, London, WC1B 3DP

Event Registration

First name
Surname
Email address
Any additional information
Post/Event URL
Post/Event Title
CAPTCHA image
Enter the code shown above in the box below.

Tag Cloud

‘fit for purpose’ obligations 2016 Adjudication adjudication lawyer Adjudication Notice Adjudication process appeal appointing an adjudicator Arbitration Artificial Intelligence Asbestos benefits of off-site construction bonfires book launch breach of contract Brexit Building Defects business interruption Business Interruption Insurance CDM CDM Regulations chambers and partners Charlotte Waters civil proceedings claim payments Claims client COMAH commercial contracts complex construction claims Compliance compulsory sprinklers in warehouses consequential loss construction Construction Construction & Engineering construction contract Construction contract dispute Construction contracts Construction dispute construction dispute lawyer construction dispute resolution construction dispute resolution solicitor construction dispute solicitors Construction Disputes Resolution Construction industry Construction Magazine contracts Contribution claim Corporate Manslaughter Corporate Responsibility costs criminal investigation criminal proceedings cut out fuse Defective Building Work Defective Premises Act developer developers disadvantages of off-site construction Disaster disaster claim Disasters Dispute dispute resolution Disputes DPA Dr Louise Smail Emergency response Emergency Response Solicitors enforcement notices Engineering Engineering dispute Environment Agency environment law Environmental Environmental Agency Environmental damage Environmental Law environmental waste EU EU Procurement Europe Evidence Expert evidence expert witness falls from height Fatal Accidents fee for intervention Fees For Intervention FFI FIDIC Contracts fine Fines Fire Fire Claim fire claims fire damage fire damage lawyers fire sprinkler systems fireworks flood flood claim flood damage food hygiene Fracking fracking claims Fraudulent claims FSW Gross Negligence Manslaughter Guide to Adjudication H&S fine increases; health and safety fines; Health & Safety health & safety breach health & safety sentences health & safety sentencing guidelines health & safety sentencing large corporations health and safety health and safety Health and Safety Executive heave Higher Fines Honey Rose v R How to appoint an adjudicator HSE Insolvency insolvent insurance Insurance Act 2015 insurance bill Insurance Broker insurance claim insurance cover Insurance Disclosure Insurance Disclosure insurance dispute insurance dispute solicitors Insurance Warranties ISO 45001 join us joint venture Judicial Review latest news Law Lawyer legal 500 legal advice privilege Legal Expense Insurance legal professional privilege legal retainers Liability Liquidated Damages Litigation litigation privilege local bodies magistrates’ courts Major Property Damage Manufacturing Martinisation material breach Mediation Michael Appleby Micheal appleby modern methods of construction (MMC) modular construction Mr. Gutaj Notice of adjudication panel firms party wall Performance Bond planning powers of an adjudicator pre-fabrication procurement procurement injunction procurement model Property Damage property danage Public Contract Public Contracts Public Contracts Regulations public procurement public procurement challenges public procurement relationship public sector Publicity Order PUWER recruitment regulation 11 Relief Resolution riot Riot Compensation Act 2016 Risk Risk Assessment safety in the workplace Sanctions Self-build sentence sentencing sentencing guidelines Serious Fraud Office SME Sneller Sony specialist risk and safety consultant Statute Barred Sub-Contractors subrogation subsidance subsidence TCC TCC Guidance team Technology and Construction Court The Adjudicator’s Decision and Costs The Enterprise Act The Lord Young Reforms The Powers Of An Adjudicator The Public Contracts Regulations 2015 The referral notice and response Training tree root UK Underwriters Warehouse insurance Warranties waste water damage WEEE What is Adjudication? what should an adjudication refal notice contain work equipment

Search The Site

Accreditations

 

The Legal 500 - The Clients Guide to Law Firms


Contact Us Now For Advice And Guidance

Enter your name
Enter your surname
Enter your Email
Ask us a Question?