Search

BLOG

Performance Bonds and Insolvency: Issues Clarified In TCC

Blog image

Ziggurat (Claremont Place) LLP v HCC International Insurance Company Plc [1]

The recent case of Ziggurat (Claremont Place) LLP v HCC International Insurance Company plc has highlighted some clear principles relating to termination provisions in JCT contracts and performance bonds.  The Technology and Construction Court (TCC) held that the contractor’s insolvency was enough to trigger the performance bond, due to a clause added by the parties to the ABI Model Form[2].  However, The Honourable Mr Justice Coulson stated that on the facts of the case, even if the amending clause had not been present, the contractor had been in breach of the construction contract (which incorporated the JCT conditions) by failing to pay the amount due to the employer following insolvency as determined under the contract.


The facts of the case

Ziggurat entered into a construction contract (JCT 2011 standard form) with County Contractors, to build a block of student flats in Newcastle Upon Tyne.

County’s performance was subject to a Performance Guarantee Bond ("the Bond"), which was provided by HCC.  The bond was based on the ABI Model Form.  Clause 1 stated that the bond could be called in should County breach the construction contract.  This clause was a standard ABI Model Form clause.  The parties added a bespoke clause (clause 2) which stated:

“(2) The damages payable under this Guarantee Bond shall include (without limitation) any debt or other sum payable to the Employer under the Contract following the insolvency (as defined in the Schedule) of the Contractor."

The following events subsequently occurred:


Ø  February 2016 – County ceased to work on the project, citing monetary problems.

Ø  14th March 2016 - Notice was given to County under clause 8.4.1 of the contract stating that the contract had been breached because; a) County had suspended work without due cause and b) they had failed to proceed with the work regularly and diligently.

Ø  County never responded to the notice and therefore Ziggurat fired them under clause 8.4.2 on 31st March 2016.

Ø  8th April 2016 – County went into insolvency.

Ø  10th March 2017 - Ziggurat made a claim against County under clause 8.7.1 of the construction contract, which included the costs of the remainder of the work having to be completed by another contractor.

Ø  17th March 2017 - Ziggurat called in the value of the Performance Bond to cover the amount claimed against County

Ø  125th April 2017 - County stated the termination notice served on them was invalid and as a result, Ziggurat was in breach of the construction contract.

The issues for the court to decide regarding the Performance Bond

The court was asked to decide whether Ziggurat could call on the Performance Bond as a result of County’s insolvency and rely on the accounting exercise, carried out by the Contract Administrator under clauses 8.7.4 and 8.7.5, to establish the amount payable under the bond.


The TCC’s decisions

It was held by the TCC that the fact County fell into insolvency was enough for Ziggurat to call on the performance bond.  This was because clauses 1 and 2 of the Performance Bond were put in place to mirror the grounds of termination in clauses 8.4 (default by the contractor) and 8.5 (insolvency of the contractor) of the construction contract, and clause 2 made it clear that HCC was liable under the bond for losses caused by County’s insolvency. 

HCC tried to argue that clause 2 was merely a subsidiary to clause 1, but this was rejected by the court on the grounds of being contrary to common sense.

The court held that even if its decision was wrong and a breach of the construction contract was required to trigger the Performance Bond, County committed a breach when it failed to pay Zuggurat following the claim made on 10th March 2017.  The Honourable Mr Justice Coulson referred to: 

Perar v General Surety and Guarantee Co[3] which stated that although insolvency did not constitute a breach of contract, failure to pay a debt due under the agreement because of insolvency did.  This is highly relevant when the triggering of a performance bond relies on the contractor to be in breach of the construction contract.

Both arguments presented by County, a) because the validity of the contract termination by Ziggurat was disputed, County was not in breach, and, b) Ziggurat’s repudiation of the contract meant that the contract had come to an end and accordingly there was no obligation to pay the clause 8.7.5 debt.

The ABI Model Form of Guarantee Bond can include the following amendment to clause 1 to ensure a contractor’s insolvency does trigger the Performance Bond:

‘For the purposes of this Guarantee Bond the expression “breach of the Contract” shall be deemed to include any failure or inability on the part of the Contractor to carry out or complete the Works in accordance with the Contract, as a result of the insolvency of the Contractor and in this case the “damages sustained by the Employer” shall include the Employer’s direct loss and expense caused by such failure or inability on the part of the Contractor’.

By inserting this, there can be no doubt that if the contractor falls into insolvency, the Performance Bond is payable, saving all parties time and money having to litigate this fact.

Fisher Scoggins Waters, are a London based law firm specialising in construction, manufacturing, and engineering law.  We have years of experience in construction contracts and insurance law.  Please phone us on 0207 993 6960 for further information.


[1] [2017] EWHC 3286 (TCC)

[2] http://www.performancebonds.co.uk/wp-content/uploads/2016/09/ABI-Guidance-about-their-standard-form.pdf

[3] (1994) 43 ConLR 110

Follow our company page on linkedin for future updates and our views on the latest developments

Please leave a comment

Enter the name you would like to appear on the comment.
(required)
Enter the email you would like to use to get updates. You email is not visible and can not be used by other users.
(required)
Enter you comment help.

 
  Post Comment

Book Launch - 27 November 2019

Will you be joining us?

HSE and Environment Agency prosecution: A new climate

27 November 2019 | Bloomsbury, 50 Bedford Square, London, WC1B 3DP

Event Registration

First name
Surname
Email address
Any additional information
Post/Event URL
Post/Event Title
CAPTCHA image
Enter the code shown above in the box below.

Tag Cloud

‘fit for purpose’ obligations 2016 Adjudication adjudication lawyer Adjudication Notice Adjudication process appeal appointing an adjudicator Arbitration Artificial Intelligence Asbestos benefits of off-site construction bonfires book launch breach of contract Brexit Building Defects business interruption Business Interruption Insurance CDM CDM Regulations chambers and partners Charlotte Waters civil proceedings claim payments Claims client COMAH commercial contracts complex construction claims Compliance compulsory sprinklers in warehouses consequential loss construction Construction Construction & Engineering construction contract Construction contract dispute Construction contracts Construction dispute construction dispute lawyer construction dispute resolution construction dispute resolution solicitor construction dispute solicitors Construction Disputes Resolution Construction industry Construction Magazine contracts Contribution claim Corporate Manslaughter Corporate Responsibility costs criminal investigation criminal proceedings cut out fuse Defective Building Work Defective Premises Act developer developers disadvantages of off-site construction Disaster disaster claim Disasters Dispute dispute resolution Disputes DPA Dr Louise Smail Emergency response Emergency Response Solicitors enforcement notices Engineering Engineering dispute Environment Agency environment law Environmental Environmental Agency Environmental damage Environmental Law environmental waste EU EU Procurement Europe Evidence Expert evidence expert witness falls from height Fatal Accidents fee for intervention Fees For Intervention FFI FIDIC Contracts fine Fines Fire Fire Claim fire claims fire damage fire damage lawyers fire sprinkler systems fireworks flood flood claim flood damage food hygiene Fracking fracking claims Fraudulent claims FSW Gross Negligence Manslaughter Guide to Adjudication H&S fine increases; health and safety fines; Health & Safety health & safety breach health & safety sentences health & safety sentencing guidelines health & safety sentencing large corporations health and safety health and safety Health and Safety Executive heave Higher Fines Honey Rose v R How to appoint an adjudicator HSE Insolvency insolvent insurance Insurance Act 2015 insurance bill Insurance Broker insurance claim insurance cover Insurance Disclosure Insurance Disclosure insurance dispute insurance dispute solicitors Insurance Warranties ISO 45001 join us joint venture Judicial Review latest news Law Lawyer legal 500 legal advice privilege Legal Expense Insurance legal professional privilege legal retainers Liability Liquidated Damages Litigation litigation privilege local bodies magistrates’ courts Major Property Damage Manufacturing Martinisation material breach Mediation Michael Appleby Micheal appleby modern methods of construction (MMC) modular construction Mr. Gutaj Notice of adjudication panel firms party wall Performance Bond planning powers of an adjudicator pre-fabrication procurement procurement injunction procurement model Property Damage property danage Public Contract Public Contracts Public Contracts Regulations public procurement public procurement challenges public procurement relationship public sector Publicity Order PUWER recruitment regulation 11 Relief Resolution riot Riot Compensation Act 2016 Risk Risk Assessment safety in the workplace Sanctions Self-build sentence sentencing sentencing guidelines Serious Fraud Office SME Sneller Sony specialist risk and safety consultant Statute Barred Sub-Contractors subrogation subsidance subsidence TCC TCC Guidance team Technology and Construction Court The Adjudicator’s Decision and Costs The Enterprise Act The Lord Young Reforms The Powers Of An Adjudicator The Public Contracts Regulations 2015 The referral notice and response Training tree root UK Underwriters Warehouse insurance Warranties waste water damage WEEE What is Adjudication? what should an adjudication refal notice contain work equipment

Search The Site

Accreditations

 

The Legal 500 - The Clients Guide to Law Firms


Contact Us Now For Advice And Guidance

Enter your name
Enter your surname
Enter your Email
Ask us a Question?