Search

BLOG

What Are The Benefits And Risks Of Adjudication?

Blog image

There is no doubt that adjudication can provide a swift, cost-effective solution to some construction disputes, preventing deadlocks and putting parties in a position where they can complete the project and make a return on their investment.  But like every process, adjudication has its complications and disadvantages.  Being aware of these can assist parties to a construction contract make the right decisions to resolve their disputes, quickly and in the most effective manner for the situation.

The right to adjudicate

A party has the right to adjudicate provided:

  • the contract is a 'construction contract' under the Housing Grants, Construction and Regeneration Act           

  • a 'dispute' has crystallised          

  • for contracts entered before 1st October 2011, it is also necessary to consider whether the construction contract is in writing


The advantages and disadvantages of the adjudication process

Adjudication is quick

Adjudication procedures have a 28-day timetable and as such may not be suitable for complex, highly technical disputes.  Parties can agree to extend the timeframe to 42 days, but even so, trying to resolve a large claim in six weeks is a tall order. 

However, the short process can have tremendous advantages.  Pre-action protocols and court proceedings can take between 12-24 months to complete.  In addition, the construction contract may include certain steps which must be completed before litigation can begin.  Adjudication can circumvent these steps and provide for a quick resolution, saving enormous amounts of time, stress and money, and limited disruption to the works.

No risk of having to pay the other side’s costs

Having a third party resolve a construction contract dispute without running the risk of paying the other sides costs if lost, will bring great comfort to any CFO.   It also means that a party with limited cash-flow can pursue its claim in circumstances where it could not have risked an adverse cost order in litigation.

However, for a strong claim, the inability to recover legal costs can reduce the net total amount recovered. A party’s irrecoverable costs in a small claim could be a significant portion of the overall claim.

Privacy

Unlike court proceedings, adjudication is private unless the adjudicator’s decision is reviewed by the Technology and Construction Court.  This allows commercially sensitive information to be more easily protected than in court proceedings, which are generally public. It can also help reduce the risk to a company’s reputation if its products, workmanship or design are found to be substandard.

The referring party has the element of surprise

Being able to swiftly issue a Notice of Adjudication is good news for the referrer, bad news for the respondent.  The referring party has an enormous tactical advantage in that they can refer a matter for adjudication at an inconvenient time for the respondent.  They can also prepare their case, gather their supporting documents and plan their strategy before serving notice of adjudication, putting the respondent on the back foot to defend their position.

The decision may be unenforceable

One major disadvantage with adjudication is that the decision may be unenforceable if the adjudicator acts outside their jurisdiction or breaches the laws of natural justice.

In summary

Like any disputes resolution procedure, adjudication has its advantages and disadvantages.  To ensure it is the right process to resolve your construction contract dispute, it is imperative to seek experienced legal advice before launching proceedings.

Fisher Scoggins Waters are a London based law firm who are experts in construction, manufacturing and engineering law.  If you would like more information about adjudication proceedings, please phone us on 0207 993 6960.

For a detailed look at each stage of the Adjudication process please read our series of Blogs:

Adjudication - The Essentials.  Part 1: What is Adjudication?

 Adjudication - The Essentials.  Part 2 :    Notice of Adjudication

Adjudication - The Essentials.  Part 3 : How To Appoint An Adjudicator

Adjudication - The Essentials.  Part 4 : The Referral Notice and Response

Adjudication - The Essentials.  Part 5 :   The Powers Of An Adjudicator  

Adjudication - The Essentials.  Part 6 : The Adjudicator’s Decision and Costs

Follow our company page on linkedin for future updates and our views on the latest developments

Please leave a comment

Enter the name you would like to appear on the comment.
(required)
Enter the email you would like to use to get updates. You email is not visible and can not be used by other users.
(required)
Enter you comment help.

 
  Post Comment

Book Launch - 27 November 2019

Will you be joining us?

HSE and Environment Agency prosecution: A new climate

27 November 2019 | Bloomsbury, 50 Bedford Square, London, WC1B 3DP

Event Registration

First name
Surname
Email address
Any additional information
Post/Event URL
Post/Event Title
CAPTCHA image
Enter the code shown above in the box below.

Tag Cloud

‘fit for purpose’ obligations 2016 Adjudication adjudication lawyer Adjudication Notice Adjudication process appeal appointing an adjudicator Arbitration Artificial Intelligence Asbestos benefits of off-site construction bonfires book launch breach of contract Brexit Building Defects business interruption Business Interruption Insurance CDM CDM Regulations chambers and partners Charlotte Waters civil proceedings claim payments Claims client COMAH commercial contracts complex construction claims Compliance compulsory sprinklers in warehouses consequential loss construction Construction Construction & Engineering construction contract Construction contract dispute Construction contracts Construction dispute construction dispute lawyer construction dispute resolution construction dispute resolution solicitor construction dispute solicitors Construction Disputes Resolution Construction industry Construction Magazine contracts Contribution claim Corporate Manslaughter Corporate Responsibility costs criminal investigation criminal proceedings cut out fuse Defective Building Work Defective Premises Act developer developers disadvantages of off-site construction Disaster disaster claim Disasters Dispute dispute resolution Disputes DPA Dr Louise Smail Emergency response Emergency Response Solicitors enforcement notices Engineering Engineering dispute Environment Agency environment law Environmental Environmental Agency Environmental damage Environmental Law environmental waste EU EU Procurement Europe Evidence Expert evidence expert witness falls from height Fatal Accidents fee for intervention Fees For Intervention FFI FIDIC Contracts fine Fines Fire Fire Claim fire claims fire damage fire damage lawyers fire sprinkler systems fireworks flood flood claim flood damage food hygiene Fracking fracking claims Fraudulent claims FSW Gross Negligence Manslaughter Guide to Adjudication H&S fine increases; health and safety fines; Health & Safety health & safety breach health & safety sentences health & safety sentencing guidelines health & safety sentencing large corporations health and safety health and safety Health and Safety Executive heave Higher Fines Honey Rose v R How to appoint an adjudicator HSE Insolvency insolvent insurance Insurance Act 2015 insurance bill Insurance Broker insurance claim insurance cover Insurance Disclosure Insurance Disclosure insurance dispute insurance dispute solicitors Insurance Warranties ISO 45001 join us joint venture Judicial Review latest news Law Lawyer legal 500 legal advice privilege Legal Expense Insurance legal professional privilege legal retainers Liability Liquidated Damages Litigation litigation privilege local bodies magistrates’ courts Major Property Damage Manufacturing Martinisation material breach Mediation Michael Appleby Micheal appleby modern methods of construction (MMC) modular construction Mr. Gutaj Notice of adjudication panel firms party wall Performance Bond planning powers of an adjudicator pre-fabrication procurement procurement injunction procurement model Property Damage property danage Public Contract Public Contracts Public Contracts Regulations public procurement public procurement challenges public procurement relationship public sector Publicity Order PUWER recruitment regulation 11 Relief Resolution riot Riot Compensation Act 2016 Risk Risk Assessment safety in the workplace Sanctions Self-build sentence sentencing sentencing guidelines Serious Fraud Office SME Sneller Sony specialist risk and safety consultant Statute Barred Sub-Contractors subrogation subsidance subsidence TCC TCC Guidance team Technology and Construction Court The Adjudicator’s Decision and Costs The Enterprise Act The Lord Young Reforms The Powers Of An Adjudicator The Public Contracts Regulations 2015 The referral notice and response Training tree root UK Underwriters Warehouse insurance Warranties waste water damage WEEE What is Adjudication? what should an adjudication refal notice contain work equipment

Search The Site

Accreditations

 

The Legal 500 - The Clients Guide to Law Firms


Contact Us Now For Advice And Guidance

Enter your name
Enter your surname
Enter your Email
Ask us a Question?