Search

BLOG

2016 Roundup – Construction Law

Blog image

Now that 2017 is here, we take a look back at some of the key developments that changed UK construction law in 2016.

Cases

Grove Developments Ltd v Balfour Beatty Regional Construction Ltd [2016] EWHC 168 (TCC), 165 ConLR 153

The Technology and Construction Court (TCC) considered whether a contractor had the right to make an interim payment application after the latest date set out in an agreed payment schedule, in circumstances where practical completion had been delayed (and, if so, whether the employer had given a pay less notice in time). 

The court stated that a contractor had no such right.  It was not possible to construe the contract (an amended JCT Design and Build Contract 2011) as including an implied term that interim payments would continue to be made after the latest date in the schedule.  The court also rejected the argument that as the payment schedule did not cover all of the works, the payment provisions of the contract did not comply with section 109(1) of the Housing Grants, Construction and Regeneration Act 1996 (HGCRA 1996). 

This case serves as a reminder to contractors to consider whether they would be able to apply for an interim payment after the dates (or stages) set out in the contract and plan accordingly.

Bouygues (UK) Ltd v Febrey Structures Ltd [2016] EWHC 1333 (TCC), [2016] All ER (D) 165 (Jun)

Mr Jonathan Acton Davis QC in the Technology and Construction Court (TCC) considered the payment terms under a subcontract based on the terms of GC/Works Subcontract. The claimant argued that the court should reject a payment schedule which did not comply entirely with the Housing Grants, Construction and Regeneration Act 1996 (HGCRA 1996) or, alternatively, incorporate a number of amendments in order to make the schedule compliant.  However, the court preferred instead to amend the schedule to make it consistent with the parties’ other payment processes and, if there was any need to replace non-compliant provisions with those from the Scheme for Construction Contracts, confirmed it would do so only to the extent necessary without overriding binding contractual arrangements that remained operative.

Cofely Ltd v Bingham and another [2016] EWHC 240 (Comm), 164 ConLR 39

In a rare decision, The Rt. Hon. Lord Justice Hamblen held that under section 24(1)(a) of the Arbitration Act 1996 (AA 1996) an arbitrator should be dismissed on grounds that circumstances existed that showed apparent bias.

Transocean Drilling UK Ltd v Providence Resources plc (The Arctice III) [2016] EWCA Civ 372, 165 ConLR 1

The Court of Appeal confirmed that the starting point for interpretation of exclusion clauses between parties of equal bargaining power is the natural and ordinary meaning of the language chosen by the parties, and where the wording is clear, it is not appropriate for the court to apply interpretive principles such as the 'contra proferentem' rule.

Legislation and protocols

The Insurance Act 2016

The Insurance Act (IA) 2015 came into force in August, radically overhauling many areas of UK insurance law, for example by updating and replacing the existing duty to disclose every material circumstance known to the insurer with a new 'duty of fair presentation'.

It is important to note that from 4 May 2017 the Enterprise Act 2016 will insert sections into IA 2015 which will imply terms into insurance contracts allowing insureds to claim damages against insurers for late payment of insurance claims if not paid within a reasonable time.

Second edition of the Pre-Action Protocol for Construction and Engineering Disputes 

The long awaited second edition of the Pre-Action Protocol came into force in November.  It brought in a number of changes, including allowing parties to agree to contract out of the Protocol. and providing that the court is only likely to sanction a party in costs for ‘flagrant or very significant disregard’ of the terms of the Protocol.  It also introduces the role of a Protocol Referee.

Third Parties (Rights Against Insurers) Act 2010

This highly-anticipated Act came into force in August. It makes it easier for a third party to issue proceedings directly against the insurer of an insolvent company, and modernises and simplifies previous legislation.

In summary

2016 saw a number of updates in cases law, protocols and legislation designed to simplify and clarify many areas of construction law.

Forecasters have predicted a significant slowdown in many sectors in 2017.  Manufacturing and construction face a tough year as uncertainty and higher costs begin to bite.  There are also serious concerns throughout both industries regarding the ability to recruit enough skilled labour once Britain formally leaves the EU. 

However, we must remember; most economists– including the likes of the Bank of England and International Monetary Fund – were wrong in 2016 when they predicted a sharp slowdown in the event of a vote for Brexit.  Although the pound plummeted and inflation rose, the economy as a whole did not tank abysmally, and enters the New Year in reasonably good shape.  On another positive note, The U.K. government recently published its infrastructure-investment pipeline, detailing a record £500 billion of projects scheduled to be undertaken in the coming years, with government investment behind 40% of the funding required.

2017 may turn out to be a year of opportunities as opposed to hardship.

We will wait and see.

Fisher Scoggins Waters are a London based law firm who are specialise in construction, manufacturing and engineering law.  To make an appointment, please phone us on 0207 993 6960.

Follow our company page on linkedin for future updates and our views on the latest developments

Please leave a comment

Enter the name you would like to appear on the comment.
(required)
Enter the email you would like to use to get updates. You email is not visible and can not be used by other users.
(required)
Enter you comment help.

 
  Post Comment

Book Launch - 27 November 2019

Will you be joining us?

HSE and Environment Agency prosecution: A new climate

27 November 2019 | Bloomsbury, 50 Bedford Square, London, WC1B 3DP

Event Registration

First name
Surname
Email address
Any additional information
Post/Event URL
Post/Event Title
CAPTCHA image
Enter the code shown above in the box below.

Tag Cloud

‘fit for purpose’ obligations 2016 Adjudication adjudication lawyer Adjudication Notice Adjudication process appeal appointing an adjudicator Arbitration Artificial Intelligence Asbestos benefits of off-site construction bonfires book launch breach of contract Brexit Building Defects business interruption Business Interruption Insurance CDM CDM Regulations chambers and partners Charlotte Waters civil proceedings claim payments Claims client COMAH commercial contracts complex construction claims Compliance compulsory sprinklers in warehouses consequential loss construction Construction Construction & Engineering construction contract Construction contract dispute Construction contracts Construction dispute construction dispute lawyer construction dispute resolution construction dispute resolution solicitor construction dispute solicitors Construction Disputes Resolution Construction industry Construction Magazine contracts Contribution claim Corporate Manslaughter Corporate Responsibility costs criminal investigation criminal proceedings cut out fuse Defective Building Work Defective Premises Act developer developers disadvantages of off-site construction Disaster disaster claim Disasters Dispute dispute resolution Disputes DPA Dr Louise Smail Emergency response Emergency Response Solicitors enforcement notices Engineering Engineering dispute Environment Agency environment law Environmental Environmental Agency Environmental damage Environmental Law environmental waste EU EU Procurement Europe Evidence Expert evidence expert witness falls from height Fatal Accidents fee for intervention Fees For Intervention FFI FIDIC Contracts fine Fines Fire Fire Claim fire claims fire damage fire damage lawyers fire sprinkler systems fireworks flood flood claim flood damage food hygiene Fracking fracking claims Fraudulent claims FSW Gross Negligence Manslaughter Guide to Adjudication H&S fine increases; health and safety fines; Health & Safety health & safety breach health & safety sentences health & safety sentencing guidelines health & safety sentencing large corporations health and safety health and safety Health and Safety Executive heave Higher Fines Honey Rose v R How to appoint an adjudicator HSE Insolvency insolvent insurance Insurance Act 2015 insurance bill Insurance Broker insurance claim insurance cover Insurance Disclosure Insurance Disclosure insurance dispute insurance dispute solicitors Insurance Warranties ISO 45001 join us joint venture Judicial Review latest news Law Lawyer legal 500 legal advice privilege Legal Expense Insurance legal professional privilege legal retainers Liability Liquidated Damages Litigation litigation privilege local bodies magistrates’ courts Major Property Damage Manufacturing Martinisation material breach Mediation Michael Appleby Micheal appleby modern methods of construction (MMC) modular construction Mr. Gutaj Notice of adjudication panel firms party wall Performance Bond planning powers of an adjudicator pre-fabrication procurement procurement injunction procurement model Property Damage property danage Public Contract Public Contracts Public Contracts Regulations public procurement public procurement challenges public procurement relationship public sector Publicity Order PUWER recruitment regulation 11 Relief Resolution riot Riot Compensation Act 2016 Risk Risk Assessment safety in the workplace Sanctions Self-build sentence sentencing sentencing guidelines Serious Fraud Office SME Sneller Sony specialist risk and safety consultant Statute Barred Sub-Contractors subrogation subsidance subsidence TCC TCC Guidance team Technology and Construction Court The Adjudicator’s Decision and Costs The Enterprise Act The Lord Young Reforms The Powers Of An Adjudicator The Public Contracts Regulations 2015 The referral notice and response Training tree root UK Underwriters Warehouse insurance Warranties waste water damage WEEE What is Adjudication? what should an adjudication refal notice contain work equipment

Search The Site

Accreditations

 

The Legal 500 - The Clients Guide to Law Firms


Contact Us Now For Advice And Guidance

Enter your name
Enter your surname
Enter your Email
Ask us a Question?